Saturday, February 21, 2009

Day 21 (Friday)

Today, Rich L and I finished the tile work - mostly grouting and polishing. Below you can see how it turned out.


Here you can see the full-extension pots and pan drawers that Hal designed and assembled.


Next up will be some end shelves for several lower and upper cabinet units that Hal is working on, as well as some cosmetic things like trim. Very cool.

Thursday, February 19, 2009

Days 17-20

A few more project preparations were done this week, mostly at the mill. Hal worked to get the pots and pans draws assembled for installation. The last couple of cabinet doors are being readied. No new pictures to post.

Today, Hal and Rich are going to work on the rest of the tiling.

The Trustees came over on Monday night to do a quick inspection and see how things were going. They seemed pleased.

Everything is fully functional and the major pieces are in place and though there is a fair bit of other work left, most of it is cosmetic.

If the tiling goes as plans, I'll post some new pictures.

Sunday, February 15, 2009

Days 14-16

A lot of the more detail work was done this week: dry wall adjustments, priming and painting. The counter tops were anchored into place and a few adjustments to some of the shelves were done.

Below you can see the tile work that has been done, mostly by Hal who said he had never tiled a wall before, but it look otherwise.

The newspaper and blue tape were optional, but I really think it helps to tie all the colors together. Plus, I can read all about the new stimulus bill.

Thursday, February 12, 2009

Days 12-13

After 2 more days of work, work mostly that doesn't show up in pictures (work down at the mill, some under the counter work), as well as some dry wall additions, the counters on the other side of the kitchen were put in place.



(that's a flashlight in the corner:)

Dick is planning on doing some more painting, then the counters will be anchored in place, and Hal and I are going to put the tile up on Saturday sometime between the morning the bone marrow drive and the Valentine's dinner in the evening.
At some point, I'll give an estimate of the contrast between what the kitchen actually, and what it might have cost if we hadn't had so much of the cabinetry donated by Barry's mill and all the labor done at no cost. I'm guessing we saved a few dollars.

Monday, February 9, 2009

Day 11

Wiring for the dishwasher was finished on Monday, along with the plumbing it requires. The refrigerator was also moved into place.






The rest of the countertop is being cut out and laminated. There is also some dry wall being cut and installed on the soffet above the sink...the kitchen was surprisingly out of square, so there have had to be some adjustments made along the way, but it is going well.


Emma helps us bake some 'treats' for the work crew which seems to be appreciated.

More later...

Saturday, February 7, 2009

Day 10

More finish work was done Thursday and Friday. One section of the counter was installed in order to get ready for the sink which was also installed - being a cast iron sink, it took 3-4 of us. I think I could have handled it on my own, but I wanted to make sure others felt involved:)

Below are a few shots of the most current work.





Andy Black came over on Friday and helped Rick W with some more plumbing and electrical.

Hal and Barry continued working on cabinets and counters.

The faucet assembly has been installed and works great!

Next will be the rest of the counter space, the last of the cabinet shelves and doors, the final plumbing work for the dishwasher, and then we'll start thinking about the rest of the more cosmetic work (tile, trim, corner shelves).

I can't say enough about how hard the guys and gals are working. It is a tremendous job that's being done and I think we're all anxious to see how it all turns out.

This is completely off topic, but below is a picture of Emma's version of the 11:00am praise team (Bumpy). We're calling it Barbie Bumpy:

According to Emma, the band members pictured above are: Craig (complete with pink guitar), Emma, Kris, Kelli, Sue and Laurie. Never thought I would be part of a church with our own action figures. Emma thanks Amanda and Rachel for the Barbie's.

Wednesday, February 4, 2009

Day 8

More shelves were installed today along with the hardware on some of the cupboard doors and drawers.


The plan is to have a fully functional sink by Friday, and work on the rest of the counter areas subsequent to that.

Tuesday, February 3, 2009

Day 7

The rest of the cabinets are all installed. Cupboard doors, shelves and drawer fronts were prepared and installed - see pictures below.



The next bit of work will be done at the mill again, cutting out the counter tops and getting them ready for installation. Plumbing is planned in preparation for the sink and dishwasher.
Eventually, some trimwork is scheduled, but their focus is getting the kitchen fully functional.
Hardware will be installed on the doors and drawers...and a large marble fountain of a Bison will be installed in the middle of the floor...just kidding:) I had a Bison burger today and I felt I should honor that somehow.

Day 6

Today (Monday) Hal and Rich installed a few more cabinets, including the sink cabinet.




Doc and Rick worked on the plumbing and electrical (not at the same time because that would be bad). Shut off valves were installed, outlets were wired in and covered and I only got nervous when Kelli said they called and asked where the fire extinguisher was.
The counter tops, cabinet doors and shelves are being worked on this week.
Everyone seems to be pleased with how things are progressing...Kelli is very excited and Emma just wants to sit in the cabinets...hmmmm.